Bid bond
Bonds are a means of protection against the non-performance of supplier. They are an undertaking by a bondsman or surety to make a payment to the client in the event of non-performance of the supplier. The cost of the bond is usually borne by the supplier, albeit, this is likely to be reflected in their tender price.
Bid bonds, also known as tender bonds, are rare in the UK, but can be a requirement of an international tender process. They are usually on-demand bonds submitted with a tender to secure the tender's commitment to commence the contract. The bond is partially or fully forfeited if the winning tenderer fails to execute the contract or meet other specified conditions.
The presence of a bid bond is intended to provide the client with the assurance that the tenderer has the financial capabilities of accepting the contract for the price quoted in their bid.
If the bond is partially or fully forfeited, the principal (typically the contractor) and the surety are jointly and severally liable for the bond, which includes any additional costs the client incurs in selecting and awarding another supplier. Often this is the difference between the lowest bid and the second-lowest bid.
However, there is the disadvantage that bid bonds can be open to abuse by the client and they may prevent smaller companies from tendering. Internationally, there have been cases of bonds 'disappearing' along with the client.
NB the UN Procurement Practitioner's Handbook, produced by the Interagency Procurement Working Group (IAPWG) in 2006 and updated in 2012, defines a bid bond or bid security as: 'A security from a supplier securing obligations resulting from a contract award with the intention to avoid: the withdrawal or modification of an offer after the deadline for submission of such documents; failure to sign the contract or failure to provide the required security for the performance of the contract after an offer has been accepted; or failure to comply with any other condition precedent to signing the contract specified in the solicitation documents.'
Capital Works Management Framework, Guidance Note, Glossary, Published by the Government of Ireland Department of Finance in 2009 suggests that: ‘A bid bond is effectively a contract of guarantee whereby the guarantor or surety (authorised to do guarantee business) undertakes to pay damages to a second party, in this case the Employer, when the Contractor does not honour his tender. In essence, the guarantor undertakes to be answerable for losses suffered by the Employer if the Contractor withdraws following a bid. The Employer does not need to prove loss before calling in this bond. When a bond is called in, the Employer has a guarantee that funds up to the amount of the bond will be available to defray the Employer’s losses resulting from the Contractor’s default.’
[edit] Related articles on Designing Buildings
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).